Our builder’s terms and conditions were payment in advance. He was very plausible and seemed honourable so we agreed to them. We have now paid for the whole of the build but phases paid for over a year ago have still not been completed. We have repeatedly asked for timescales and we are now in month 21 but the builder refuses to give any timescales and we are desperate to be in our home. At the beginning of the project he estimated 9 – 12 months to completion. Please can you advise on the best course of action as we need him to be cooperative. Whenever we put any pressure on he becomes even more difficult and resistant. Many thanks

===========================

Answer:-

It sounds like such a stressful situation, especially after trusting the builder and paying everything upfront. A 9–12 month build stretching into 21 months with no clear timescales is definitely not reasonable, and you shouldn’t be left in the dark like this.

At this stage, the best thing you can do is move everything into formal written communication. When things are only said verbally, builders like this tend to avoid responsibility. But once something is put in writing, it becomes much harder for them to ignore.

I’d suggest sending a calm but firm letter (recorded delivery) summarising the delays and asking for a clear timetable for the remaining work. Under UK law, even if the contract didn’t set deadlines, the work still has to be done within a reasonable time — and 21 months isn’t reasonable.

If he still refuses to cooperate, it may help to bring in a RICS surveyor or construction professional to review what’s left and speak to the builder on your behalf. Builders usually take things a lot more seriously when someone official gets involved.

Hopefully he responds once things become more formal, but if not, you can look at a solicitor’s “letter before action” as a next step. You shouldn’t have to keep living like this, especially when the build is already fully paid for.

==========================